General
Many products in Division 14 will require some type of support or blocking for installation not included with the item itself. Examples are supports for conveyors or tube systems, attachment points for lifts, and footings for hoists or cranes. Add these supports in the appropriate division.
14100
Dumbwaiters
14200 Elevators
Dumbwaiters and elevators are estimated and purchased in a method similar to buying a car. The manufacturer has a base unit with standard features. Added to this base unit price will be whatever options the owner or specifications require. Increased load capacity, additional vertical travel, additional stops, higher speed, and cab finish options are items to be considered. When developing an estimate for dumbwaiters and elevators, remember that some items needed by the installers may have to be included as part of the general contract. Check the job specifications and drawings before pricing.
Examples are:
|
|
Shaftway |
|
Electrical Connections |
|
|
Rail Support Brackets |
|
Pits |
|
|
Machine Room |
|
Roof Penthouses |
|
|
Electrical Supply |
|
Pit Ladders |
|
|
Sill Angles |
|
|
Installation of elevators and handicapped lifts in historic structures can require significant additional costs. The associated structural requirements may involve cutting into and repairing finishes, mouldings, flooring, etc. The estimator must account for these special conditions.
14300 Escalators & Moving Walks
Escalators and moving walks are specialty items installed by specialty contractors. There are numerous options associated with these items. For specific options contact a manufacturer or contractor. In a method similar to estimating dumbwaiters and elevators, you should verify the extent of general contract work and add items as necessary.
14400 Lifts
14500 Material Handling
14600 Hoists & Cranes
Products such as correspondence lifts, conveyors, chutes, pneumatic tube systems, material handling cranes and hoists as well as other items specified in this subdivision may require trained installers. The general contractor might not have any choice as to who will perform the installation or when it will be performed. Long lead times are often required for these products, making early decisions in scheduling necessary.